|
Pali PTP Sdn Bhd v Bond M&E Sdn Bhd and another appeal [2023] 6 MLJ 176 Court of Appeal Building and Construction Law — Construction Industry Payment and Adjudication Act 2012 (‘CIPAA’) — Payment dispute |
|
| Facts of the case |
|
| Issues |
|
| Ratios |
(1) Whether a subcontractor must prove non-payment by the main contractor before seeking payment directly from the principal under section 30 of the CIPAA. (a) The Court of Appeal held that under section 30 of the CIPAA, a subcontractor is not required to provide affirmative proof that it has not been paid by the main contractor. (b) By applying section 30, the Court found that non-payment is presumed once the subcontractor issues a valid written request for direct payment. The statutory burden then shifts to the principal to enquire with the main contractor and require proof of payment under subsection 30(2). If the principal fails to do so, it is obligated to make direct payment to the subcontractor. (c) The Court reasoned that this interpretation aligns with the object and purpose of the CIPAA to ensure prompt cash flow and efficient payment in the construction industry. Requiring subcontractors to produce proof of non-payment would defeat this legislative intent by creating unnecessary procedural hurdles. (d) Relying on PCom Pacific Sdn Bhd v Apex Communications Sdn Bhd & Anor [2020] MLJU 118 and HSL Ground Engineering Sdn Bhd v Civil Tech Resources Sdn Bhd [2021] 8 MLJ 347, the Court reaffirmed that failure by a principal to issue the statutory notice under subsection 30(2) of the CIPAA amounts to acceptance of liability for direct payment. (e) Accordingly, Bond’s claim of non-payment was sufficient. Pali’s failure to verify or issue a statutory notice meant that Bond’s right to direct payment became enforceable, and Pali was statutorily bound to make payment. The Court emphasized that section 30 of the CIPAA must function effectively to ensure prompt payment and maintain cash flow in the construction industry. (f) Thus, Pali’s defence failed, and the Court affirmed that Bond was entitled to direct payment under section 30 of the CIPAA. (2) Whether the term “adjudicated amount” under section 30 of the CIPAA extends to interest and costs, or is limited to the principal sum awarded. (a) The Court allowed Bond’s cross-appeal, holding that the High Court erred in excluding interest and costs from the meaning of “adjudicated amount”. (b) Although the term “adjudicated amount” is not defined in section 4 of the CIPAA, the Court adopted a purposive interpretation in accordance with section 17A of the Interpretation Acts 1948 and 1967 [Act 388], which requires that legislation be interpreted in a manner that advances its underlying purpose and objective. (c) The Court referred to Tebin bin Mostapa v Hulba-Danyal bin Balia & Anor [2020] 4 MLJ 721, in which it was held that ambiguous statutory expressions must be construed in accordance with the intention of the legislature. The purpose of the CIPAA, as stated in Jack-In Pile (M) Sdn Bhd v Bauer (M) Sdn Bhd [2020] 1 MLJ 174, is to facilitate regular and timely payments and resolve payment disputes quickly and economically. (d) The Court also cited ACFM Engineering & Construction Sdn Bhd v Esstar Vision Sdn Bhd [2016] MLJU 1776, which explained that the CIPAA is a remedial statute intended to protect small contractors who are at risk of delayed or withheld payments. (e) Further, the Court examined the Parliamentary Debates during the Second and Third Readings of the Construction Industry Payment and Adjudication Bill 2011, which emphasized that the Act was enacted to safeguard subcontractors and ensure continuous cash flow. (f) Therefore, the Court held that “adjudicated amount” in section 30 of the CIPAA must be read holistically to include all monetary components awarded by the adjudicator. |
| Decision | The Court of Appeal delivered a unanimous decision:
|
| Key Takeaways |
|
Full of judgement of this case can be obtained from Lexis Advance.


